Analysis of Time Overrun and Alternative Solutions using The DMAIC Framework in The 8Th-Floor Electrical Installation Project at Mall X
DOI:
https://doi.org/10.55324/josr.v5i9.3381Keywords:
Time Overrun, Earned Value Management (EVM), Critical Path Method (CPM), Schedule Variance (SV), Standard Operating Procedure (SOP)Abstract
Time overrun is one of the most critical challenges affecting schedule performance in construction projects. This study aimed to identify the factors contributing to time overruns, evaluate schedule deviations using Earned Value Management (EVM), and propose improvement strategies through the Critical Path Method (CPM) within the DMAIC (Define, Measure, Analyze, Improve, Control) framework for the electrical installation project on the 8th floor of Mall X. A mixed-methods approach was employed by combining primary data obtained from interviews with the Project Manager, Site Engineer, Supervisor, and Quality Control personnel with secondary data from project schedules, S-curves, and progress reports. The analysis was conducted using Schedule Variance (SV), Fishbone Diagram analysis, CPM simulation, and the development of a Standard Operating Procedure (SOP). The results showed that time overrun factors included Design, Material, Management, Method, and Man, with Design, Material, and Management identified as the dominant factors (100% occurrence frequency), followed by Method (75%) and Man (50%). EVM analysis indicated that schedule deviation began in week 11, with an SV of ?12.44% at the planned completion in week 17, indicating that actual progress reached only 87.56% of the planned progress and resulted in completion delays until week 20. The CPM simulation identified the critical path A–B–D–H–K–N–O with a total duration of 103 working days (approximately 15 weeks), compared with the existing 17-week schedule based on practical experience without structured scheduling methods, indicating a potential reduction of two weeks. This study proposed CPM implementation and an SOP for Project Schedule Performance Control to minimize time overruns in similar construction projects.
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Siti Nurul Afina, Syamsir Abduh, Hakimul Batih

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International.
Authors who publish with this journal agree to the following terms:
- Authors retain copyright and grant the journal right of first publication with the work simultaneously licensed under a Creative Commons Attribution-ShareAlike 4.0 International (CC-BY-SA). that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal's published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.